Material moves by road from Miriyan to Kalaburagi ICD, then to Chennai (INMAA) for sailing. Everything below is measured from live shipments rather than from a schedule.

01 / Route

Route and transit

Load port
Chennai

INMAA

Inland depot
Kalaburagi ICD

Road leg 610 km

Fastest UK port
28 days

Felixstowe, weekly service

Containers / month
26

Current committed capacity

Ex-order to UK port
52–64 d

Including production

Reported breakage
0.7 %

By area, last 12 months

Transit times by discharge port
Discharge portTransit daysService frequency
Felixstowe28–32Weekly
Southampton29–33Weekly
London Gateway30–34Fortnightly
Liverpool33–37Fortnightly
Dublin34–38Fortnightly
Lead times by stage
StageDuration
Order confirmation to cutting start3 working days
Cutting, calibration and finishing12–18 days per container
Crating, marking and inland haulage5 days
Port cut-off to sailing4–7 days
Total ex-order to UK port52–64 days

02 / Loading

Container loading

Payload is the binding constraint on stone, not volume. Loading is calculated to keep the unit legal on the UK road leg.

Container types and quantities
ContainerPayloadAreaCrates
20 ft GP27.5 tApprox. 480 m² at 20 mm14–16
40 ft GP27.5 tApprox. 470 m² at 20 mm14–16
20 ft GP (30 mm)27.5 tApprox. 320 m² at 30 mm12–14
Container quantities per stone
StoneCrates per 20 ftArea per 20 ftCrate gross
Shahabad Grey15480 m² at 20 mm1,780 kg gross at 20 mm
Shahabad Yellow15475 m² at 20 mm1,745 kg gross at 20 mm
Shahabad Maroon14445 m² at 20 mm1,830 kg gross at 20 mm
Shahabad Cream16505 m² at 20 mm1,690 kg gross at 20 mm
Forklift loading crated limestone slabs into a twenty foot shipping container at an inland depot
Two-row stuffing with dunnage between rows and against the doors

03 / Crating

Crate specification

Fixed internal geometry across the range so that handling equipment and racking do not change between stones.

Crate construction specification
Internal geometry1180 × 780 × 950 mm
TimberHeat treated, ISPM 15 stamp IN-KA-2287
Slab orientationOn edge against a braced back panel
Separation5 mm closed cell foam between faces
Edge protectionCorner angle on all external edges
StrappingFour steel bands, tensioned and sealed
MarkingBatch, stone, finish, thickness, area, net weight, two faces
Gross weight range1,690–1,830 kg
Timber export crates loaded with grey limestone slabs stood on edge with steel strapping
Crated material awaiting inland haulage

04 / Terms

Quotation and minimums

Kept deliberately simple.

Quotations are issued to your nearest port or delivered to your yard, on request. Both are quoted per square metre with all handling stated on the face of the quotation.